Bugfixes:
- MSP-FR: Docking between PV modules works again. In case of previous errors, the design must be saved again and then the modules can be docked again.
- MSP-FR: The PDF output in CAD plan and structural analysis is now complete again.
-
Features:
- MSP-FR: Input of friction coefficient 0 is no longer possible.
Bugfixes:
- Solrif: Edge profiles are drawn correctly.
- MSP: Various language errors in foreign languages fixed.
- All: eHora connection.
Changes:
- MSP-FR: Optimizations in the ballast distribution.
-
Bugfixes:
– MSP-PR: Standing seam roof: Error in material selection fixed.
Changes:
MSP-PR: From Tuesday, 09.04.2024, an additional support channel with a length of 3.55 m will be added to the currently available MSP-PR-CH support profiles => Both lengths (3.30 m and 3.55 m) can be planned. The supply principle changes from stock-led to demand-oriented. The delivery period for the 3.30 m beam profiles is now 4-6 weeks.
MSP-PR: From Tuesday, 09.04.2024, the following 3.30 m long inlay profiles MSP-PR-IC(B) will be replaced by a new inlay profile with 3.55 m => The 3.30 m long inlay profile is no longer plannable.
- Inlay profile MSP-PR-IC 30
- Inlay profile MSP-PR-ICB 30
- Inlay profile MSP-PR-IC 35
- Inlay profile MSP-PR-ICB 35
- Inlay profile MSP-PR-IC 40
- Inlay profile MSP-PR-ICB 40
-
Features:
- MSP-FR: Explanation “Max. foot pressure” in results table.
- MSP-FR: Show border area also with “Show background”.
Bugfixes:
- MSP-FR: Fixed over ballasting of individual blocks on large roofs.
- MSP-FR: Load-bearing capacities of center clamps increased in accordance with general building authority approval.
- Solrif: Option “ground connector” has been activated again.
Changes:
- MSP-FR: Clear display of cp values.
- MSP-PR: Reset of snow load when changing the roof pitch. When saving, the “Snow load” field is highlighted in red and the following comment is displayed “Snow load [kN/m²]* (si=μi*sk) is mandatory!”.
- MSP-PR/FR: Reset the wind load when changing the building height. When saving, the “Wind load” field is highlighted in red and the following comment is displayed “Wind load [kN/m²]* (qp, peak velocity pressure) is mandatory!”.
-
Features:
- MSP-PR: Optimizations in the design of the roof hooks.
- MSP-FR: “Generate ballasting plans separately” information text improved for large roofs.
- MSP-FR-G: Maximum permissible number of stones on the connecting rails reduced.
- Solrif: Minimum size of blind modules adjusted.
Bugfixes:
- MSP-FR: Reference height for wind load: Error in unit corrected.
- MSP-FR: Restrictions for second ballast tray corrected.
- MSP-FR: Corrected translation error in the “Construction” menu.
Changes:
Long wind deflector (MSP-FR-S)
- Module length range south is adjusted to 1620-2399 mm.
- The new long wind deflectors (length from 1815 mm to 2399 mm) are now automatically designed in the SPT.
- Additional information can be found in the technical data sheet.